Reporting for others:
After the door was removed yesterday, this morning Travis, Mark and Tyler installed the Install Arm onto the chamber flange (right hand side when viewing it from standing outside of the chamber). They also mounted the 5-axis table and the elevator lift to the arm, in prep for removal of the ETMY lower portion of the QUAD.
When they were finished, I helped Jim with the chamber entry contam control(picking up 3" wafer and 1" witness optic from floor to stow, and wiping floor and in-chamber stool). He then locked the ISI.
Rick, Evan, Travis and Darkhan are next up to transition to Laser Haz, go in chamber, set up the PCAL target on the ETMY SUS and look for the beam coming in and out.
Meanwhile, the welding cleanroom outside of the chamber and a staging room for parts prep have been setup and cleaned a few times over the last ~week+. We have moved all of the SUS equipment to the VEA and are in the process of staging it for the work.