TITLE: 01/17 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: MAINTENANCE DAY
LOG:
All times marked in UTC:
17:23 Bubba and Mark into LVEA for rigging in preparation for scaffold assembly
17:46 Coca-Cola on site
17:55 Bubba and Mark out
16:00 Jeff to cleaning area and LVEA
16:05 Terry out to squeezer bay
16:30 Pest control on site. Chris escorting them into LVEA.
16:40 Jeff out of LVEA
16:45 Chris escorting pest control down the Y arm to out stations
17:00 Terry out for vent meeting
17:05 Chandra out going to EY
17:15 Norco with LN2 going to vessel ending in 77
17:55 Corey out to Optics Lab
18:00 Terry back out to squeezer bay. Nutsinee, as well.
18:03 Jim and Hugh out to EY to work on HEPI pumps
18:10 Resetting BSC watchdogs tripped from recent earthquakes
18:16 Keita out to floor checking cabling on IO2TL; Sheila taking IMC open loop meaurements; Cheryl is addressing cameras
18:17 Mark and Tyler out to HAM2 to assess the newly installed catwalk and address access options
18:20 Jenne out to join Sheila Keita and Cheryl
18:22 TJ out to optics lab
18:22 Marc to CER to investigate AS WFS read-backs WP#7294
18:23 Travis out to Biergarten
18:35 Mark and Travis out
18:41 Pest control is done
18:53 Mark and Tyler to EY
19:07 Corey out of the optics lab
19:19 Jim and Hugh back from EY
19:21 Sheila out
19:39 Jenne out to IO2TL
19:40 Chandra out to LVEA
21:03 Jeff B out to both end stations - mechanical rooms
21:10 Nutsinee out to squeezer bay
21:22 Betsy and Travis out to Mid-X
21:27 Karen out to the optics lab
21:29 TJ bac out to optics lab
21:29 Jenne out to IO2TL
21:40 Betsy and Travis out to EX
22:06 Marc out
22:30 Sheila out to LVEA with Jenne
22:42 Hugh back
22:46 Chris headed back to corner from EX
23:26 Marc to MY