H1 General
edmond.merilh@LIGO.ORG - posted 09:58, Tuesday 16 January 2018 (40133)
Vent Meeting Minutes

EY Work:

IO: HAM 2 & 3 area

Maintenance: DAQ rebooting and other work interfering with commissioning.

Squeezer: still needs cables routed to HAMs 5/6

ITM Camera install and TCS chiller work done; TCS LASER is back ON

Keita wants illuminators on HAM chambers 2 & 3

Jeff B re-configuring dust monitors prior ro any DAQ restart

CDS Computing: Security updates are ongoing

Beckhoff work: ongoing