EY Work:
- ion pump removal: DONE
- EY will have a designated NHZ zone curtained off with "at height" restrictions
- EY work will require good coordination due to limited space.
- EY lock and tag outs for green LASERS Current status is LASER SAFE
- End Station: HEPI work ongoing. Work Permits covered
IO: HAM 2 & 3 area
- Scaffold/platform is up. There is some discussion about the ladder access/type.
- Permanent cameras are being installed as well as temporary.
- HEPI was locked for work and is now currently UNLOCKED.
- Mode cleaner locking: ongoing more measurement and adjustments to be made
Maintenance: DAQ rebooting and other work interfering with commissioning.
Squeezer: still needs cables routed to HAMs 5/6
ITM Camera install and TCS chiller work done; TCS LASER is back ON
Keita wants illuminators on HAM chambers 2 & 3
Jeff B re-configuring dust monitors prior ro any DAQ restart
CDS Computing: Security updates are ongoing
Beckhoff work: ongoing