TITLE: 01/24 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:13 Terry out to squeezer bay
16:18 Karen and Vanessa out to EY to clean
16:39 Fil out to HAM2 area - camera images not getting into cr
17:00 Vanessa and Karen back from EY
17:10 Mark and Tyler out to MX to retrieve magnets
17:12 Travis, Danny, Angus and Karl (welding crew) out to EY
17:20 Jason out to PSL enclosure.
17:27 Karen and Vanessa cleaning in LVEA
17:30 Marc out to LVEA - ZM work at output arm
17:31 Fil out
17:51 Jeff B heading out to PSL enclosure - leak in chiller manifold
18:10 Jason back from PSL enclosure and out to EY for Fiber Welding.
10:32 Sheila out to optics lab
19:06 Mark and Tyler back and out to LVEA - moving ION pump
19:08 Peter going out to PSL enclosure - to secure environmental controls after leak repair is done
20:00 Welding crew and Sheila back and out for lunch
20:30 Peter ad Jeff B out to ITMX - camera
21:05 Peter and Jeff back
22:00 Site Meeting