andres.ramirez@LIGO.ORG - posted 08:41, Thursday 30 August 2012 (4030)
Start of H1-HSTS-PRM Phase 1b Testing. OSEMs Data.
H1-HSTS-PRM is ready for Phase 1b testing. OSEMs have been centered and tested. Check the attached file for data on Open Light Values, Offsets, Gains, etc.