Vent Meeting Minutes
Commissioning:
HAM6 OM alignment next two days
Make sure ALS is working
ISCT1 alignment
IR-only glasses no longer okay
PSL deferred
Flange needs final torquing at HAM6
HAM6 South door off as prep for VOPO
During X-arm Feb 6th comm work-No entry to HAM6, no VP work
ZM1 install on hold
ITM camera install, images on both, need to lock them down
Tuesday Feb 30th-Laser Safe 7-10AM
CDS:
ITM work
Take CS Beckhoff down, scan for hardware
End-Y:
PCal install vibration absorber
Later this week NGG pump commissioning
HEPI end station filter change ongoing
Mid-Y:
Expect alarms for vacuum work
End-X:
Conduit work
Take ion pump off