corey.gray@LIGO.ORG - posted 12:41, Tuesday 06 February 2018 (40436)
Mid Shift Status
LVEA's GV7 for the X-arm opened just after 8am.
Green beam from EX seen at LVEA's ITMx shortly afterward. Need to align all optics upstream to allow IR light to shine back to EX.
PSL Shutter opened for IR light.
ETMx Seismic Table tripped. This was later determined to be due to manlift moving outside of the building and drilling (Ken electronics work); this work was stopped.
The Seismic DMT viewer was down for first few hours (Dave & Jonathan worked on getting it back).
Alignment work continues during the lunch hour....