Reports until 09:23, Monday 12 February 2018
LHO General
thomas.shaffer@LIGO.ORG - posted 09:23, Monday 12 February 2018 (40494)
Morning Meeting Minutes

PSL

    Starting 70W amp work after meeting.

Commissioning

    HAM6 looks good, DRMI was locked. Looking at HAM6 South door removal this week, as well as placing ISCT6 being placed just outside the cleanroom. Will capture SDF.

Vac

    MY CP4 work continues; craning, electrical, and piping work.

    More discussion on the HAM6 septum view port cover.

EX

    Activity will be ramping up at this end station, including: prepping cleanrooms, prepping weld room, PCAL alignment, ALS power supply, staging equipment, VE interlock.

Film crew will be on site Thursday Friday.

Will be going laser SAFE until we need lasers for commissioning. Work Safe!