Cryopump #4 reservoir is empty and the pressure at CP4 started to rise as a result - currently at 9.4e-8 Torr, and tapering off. Kyle closed the main LN2 draw valve outside to ensure no LN2 was seeping past the LLCV.
A second scroll pump is running and valved out at the bottom right angle valve on CP4, just in case the primary turbo scroll fails. Turbo has a fan for cooling.
GV 11 was completely stripped of all annulus piping today and more fiberglass insulation was removed from the GN2 lines (mid-y station needs a good cleaning).
CP4 Dewar will get filled next Tuesday.
Another change order to bake enclosure design is being worked out. Still plan to start installation Tuesday, the 20th.