TITLE: 02/15 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
Wind: 4mph Gusts, 2mph 5min avg
Primary useism: 0.22 μm/s
Secondary useism: 0.24 μm/s
QUICK SUMMARY:
- 15:30 Mark is at EX, and I'm assuming he is charging/moving the Man Lift because dust counts have made another big jump up.
- [edit: Dirty work is currently going on at EX to prep for cleaning & opening up BSC9. On camera I see Mark moving around on the manlift & dust monitors are back in the green.]
- 16:00 MidY's CP4 work continues (Chandra)
- Low frequency seismic DMT still has issues (but all Control Room computers will be upgraded in the coming weeks, so hope to get this going after the upgrade.
- [edit: Ken working at MY.]