PSL: So far, so good.
Commissioning: On Hold mostly, except for SDF clean-up onging
EY/ETMy:
- Coming up: ETMy alignment work, PCal alignment
- Possible binary IO card swap regarding readback channel (Fil)--deferred until later
EX/ETMx:
- GV20 closed, cleanroom moved, staging continues. (More of the same next week)
- Locking down of HEPI next week (Hugh)
- Oplev recentering needed, probably tomorrow/Fri. (Ed)
HAM6/Squeezer:
- TODAY: TJ & HUGH--Removing mass from table & attaching fixtures to arm (Be careful if moving arm, has hazard analysis & more than one person)
- Squeezer: Optical measurements in optics lab, VOPO balancing/prep work
- ISCT6 table: Discussed readiness for craning ISCT6 to north side of HAM6 cleanroom possibly Fri.
Vacuum:
- Next Tues/Wed MCE here to install oven
- EX vent: Take off ion pump as first item for vent
Maintenance:
- ISI Model--deferred
- SUSEY RCG boot--deferred
- Framewriter work
- DAQ restart (adding SR3 ROC)
Other:
- Kyle requested a chiller
- Table blocking emergency exit, Nutsinee will correct this.
- Strip Tool of MY CP4 pressure sensors on video0--->Keep this for a couple of months (VAC crew monitor this online).
- Discussion about possible corner station vent to fix ITMy SUS. (occurred after meeting)