TITLE: 02/16 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
It was decided the corner station will be vented on Tues. 7.5 Magnitude EQ from Mexico ended the shift. Sheila is still in the Optics Lab doing Squeezer measurements.
LOG:
- ~15:00 Film crew escorted around site by Thomas
- ~ Electrical work at MY (Ken D)
- 15:04 Removing BSC Arm at EY (Mark D, Chris S, joined by Travis)
- 15:09 Prepping for ISCT6 move (Terry)
- 15:53 H1PSL enclosure (Peter, Bartlett, Jason joining @17:20)
- 19:30 Bartlett & Jason return to work on chiller plumbing
- 17:16 LSC front end went down (I didn't notice until Dave walked in to tell me about a very RED CDS Overview).
- Recovery involved Dave, Jeff, myself, Greg...
- 19:05 Resetting TCS laser controllers which went down due to chillers (Greg)
- 17:30 Running cable at EX (Ed & Marc)
- 17:48 MY visit (Chandra & Gerardo)
- 17:52 Craning items (Mark,TJ)
- 18:07 ISCT6 measurements (Nutsinee, Terry, Daniel?)
- 19:59 out for lunch (Nutsinee)
- 18:10 Working on ETMy at EY(Betsy, Travis)
- 18:23 Disconnecting high voltage for Squeezer (Fil)
- 19:07 Trip to CER to check on cables (Ed, Fil)
- 19:32 Trip to CER to look at SR3 Oplev (Kissel)
- 20:30 Tour in LVEA (Betsy)
- 21:01-22:50 Forklift from LVEA to MY & EX light bulbs (Mark D)
- 21:09 Scanning HAM6 racks (Elizabeth)
- 21:18 - 21:08 Craning ISCT6 in place...used 10' straps. (Nutsinee, Terry, Daniel, Corey)
- Afteward Squeezer crew prepped the table just outside the HAM6 cleanroom.
- Patrick covered "the chair" while I was craning. Here are activities when away:
- 21:18 Sheila to optics lab
- 21:26 - 21:40 Betsy taking guests to roof
- 21:28 Hugh to HAM6 area
- 21:43 Marc and Filiberto to HAM6 area for cable testing
- 21:53 Elizabeth to CER
- Staging PSL's HPO for drying it out with dry nitrogen (Jeff & Peter)
- 22:19 Restart EY BRS computer because it was rung up this morning (Patrick & Jim)
- 22:43 Testing cables (Hugh, Fil, Marc)
- 23:00 Working in H1 PSL Enclosure (Jason)
- 23:03 Powering Beer Garden cleanroom for next week's Corner vent (Mark D.)
- 23:48 Magnitude 7.5 EQ warning: On ISI Config, I hit the "VERY LARGE EQ" button & said "y". I think this didn't do much since after losing LSC earlier today, all the ISIs were transitioned to ISI_DAMPED_HEPI_OFFLINE.
- 23:59: Noticed OBSERVATORY MODE was LOCKING....it must have come back this way after the LSC front end crash this morning. Returned it to PLANNED ENGINEERING.
- 23:59 MY work (Fil & Gerardo)