yannick.lecoeuche@LIGO.ORG - posted 13:23, Thursday 22 February 2018 (40669)
Thursday Vent Meeting Minutes

Corner:

PSL going well, working on wiring

CER ISC cabling almost finished

ISCT6 cable connection finished

VOPO balanced and cabled

HAM6 feedthru proof, function testing

EX:

Staging at End-X planned for upcoming week

EY:

Installs at End-Y planned for next week

PCal alignment check complete

MY:

MCE electrical being finished, will begin testing

HAM6:

No in-chamber work during pump down

VOPO install Monday

Tuesday Maintenance:

SDF work complete

ISI Model

SUS EY RCG Boot

Framewriter work

DAQ restart