Corner:
PSL going well, working on wiring
CER ISC cabling almost finished
ISCT6 cable connection finished
VOPO balanced and cabled
HAM6 feedthru proof, function testing
EX:
Staging at End-X planned for upcoming week
EY:
Installs at End-Y planned for next week
PCal alignment check complete
MY:
MCE electrical being finished, will begin testing
HAM6:
No in-chamber work during pump down
VOPO install Monday
Tuesday Maintenance:
SDF work complete
ISI Model
SUS EY RCG Boot
Framewriter work
DAQ restart