AlenaA, StephenA, NikoL, MarekS, JimW, RickS
- Four camera view relay mirrors and bases removed from periscope structure.
- Four vibrations dampers installed in nominal locations per D1200174
- 1/4-20 flathead screws replaced in backside of periscope (where dampers were installed earlier)
- All Shield Mt. brackets (D1700220) installed per drawings. One FHCS on back side could not be removed, so one of the 220 brackets is installed with just one 1/4-20 SHCS
- Barrel baffles installed
- Four inner shield panels installed
- Two larger outer shield panels not yet installed. Plan to install them tomorrow morning.
- Test of spare flexure inside A7 adapter revealed that the un-compressed gap between the center of the flexure and the A7 wall is about 0.265”, not 0.300” as measured in the SolidWorks model.
- We plan to do a quick Pcal beam alignment check first thing in the morning, then install the remaining baffles, then adjust the periscope flexures.
Baffles and shields installed for fit check on LIGO India Xarm periscope in Staging Building.
Photo attached.
Work completed: LHO aLOG 40777
Build records: T1800172