Ops Day Shift Summary
Ops Shift Log: 03/06/2018, Day Shift 16:00 – 08:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for vent work
Intent Bit: Engineering  
Support: X
Incoming Operator: N/A
Shift Summary:  Upgrades, improvements, and commissioning work continues in the corner station, both end stations, and Mid-Y
 
Activity Log: Time - UTC (PT)
15:43 (07:43) Port-a-Potty on site to service portables
16:00 (08:00) Start of Shift
16:03 (08:03) Jeff K., & Georgia – Going to End-Y for magnet field measurements
16:26 (08:26) Chris – Escorting pest service around site
16:47 (08:47) Filiberto – Rerouting cables for Vacuum gauges atop HAM6, BSC5, BSC6 (WP #7402)
17:29 (09:29) Norco on site to due survey of Nitrogen tanks
17:30 (09:30) Jim & Ed – Going to End-X. Ed resetting DM VEA2
17:37 (09:37) TJ – Going to HAM6
17:41 (09:41) Filiberto – Finished at HAM6
17:44 (09:44) Filiberto & Richard – Into Optics Lab to test OSEM
17:48 (09:48) Betsy & Corey – Going to Mid-X to get some cases
17:48 (09:48) Joel from RDO on site to see Bubba
17:54 (09:54) Gerardo – Working on Getter pump under fume hood in Optics Lab
17:55 (09:55) Sheila – Going to HAM6
18:03 (10:03) Terry – Going to HAM6
18:05 (10:05) Bubba – Going into the LVEA
18:10 (10:10) Jason & Rick – Going to HAM6 area to recover laser viewer
18:15 (10:15) Bubba – Out of the LVEA
18:19 (10:19) Betsy & Corey – Back from Mid-X
18:20 (10:20) Rick & Jason – Out of the LVEA
18:22 (10:22) Filiberto & Richard – Out of the Optics Lab
18:34 (10:34) Filiberto – Going to End-X for Vac gauge wire re-routing (WP #7402)
18:52 (10:52) Cintas on site to service mats
19:00 (11:00) Jason & Ed – Going into the PSL enclosure for 70W alignment
19:05 (11:05) Corey & Niko – Going to HAM6
19:11 (11:19) Dave B., - Doing model changes for Sheila – (WP #7395)
19:18 (11:18) Joel from RDO on site to see Bubba
19:22 (11:22) Paradise Water on site to deliver water
19:26 (11:26) Karen – Leaving Mid-Y coming back to CS
19:28 (11:28) Matt H. – Going into PSL enclosure
19:56 (11:56) Corey & Niko – Out of HAM6
20:01 (12:01) TJ – Out of the LVEA
20:02 (12:02) Dave B. & Hugh – SEI model changes
20:13 (12:13) Jeff K. & Georgia – Back from End-Y
20:18 (12:18) Jason, Matt, & Ed – Out of the PSL enclosure
20:42 (12:42) Betsy – Going to End-Y
20:54 (12:54) Dave B. – DAQ restart
21:15 (13:15) Filiberto – Finished at End-X
21:33 (13:33) Filiberto – Going to End-Y for ground loop checks and vac cabling (WP #7402)
21:40 (13:40) Jason, Matt, & Ed – Going into the PSL enclosure for 70W work
22:24 (14:24) Apollo crew – Mid-Y to get snorkel lift and move it to End-Y
22:26 (14:26) Jeff K. & Georgia – Returning equipment to the LVEA
22:42 (14:42) Sheila – Going to HAM6
22:43 (14:43) Betsy – Back from End-Y
22:45 (14:45) Filiberto – Back from End-Y
22:58 (14:58) Jason, Matt, & Ed – Out of the PSL enclosure
00:00 (16:00) End of Shift