Reports until 16:09, Friday 09 March 2018
H1 General
Link
cheryl.vorvick@LIGO.ORG -
posted 16:09, Friday 09 March 2018
-
last comment - 16:51, Friday 09 March 2018
(40937)
Shift Summary:
State of H1:
EY: vented, first contact applied
MY: bake continues
CS:
HAM6/SQZ:
in-chamber work at HAM6 is complete, or close to complete
ISCT6 is sitting on the North side of the chamber and is wired up
the SQZ table is on the South side of the chamber and is being commissioned
TCSX: the laser was turned on today
MX: card access work continued today
EX: Pcal baffle work
all optics aligned, except ETMX and TMSX which are damped
all SEI platforms that aren't locked are in damped or states above damped (robust_isolated)
SEI config is in Large EQ NOBRSXY
Activity Detail:
09-03-18 15:12 Marm and Mark craning the lift over the beam tube in LVEA, under 500lbs
09-03-18 16:31 Fil to EY to work on access system
09-03-18 16:35 Mark to EY to get the snorkle lift and bring back to the CS
09-03-18 17:07 Mark to CER and LVEA to trace a cable
09-03-18 17:16 Mark is done moving the snorklelift
09-03-18 17:30 APS is at MX
09-03-18 17:37 Jim, Marer, Niko, Corey, to EX for Pcal baffle install
09-03-18 17:58 Ken to EY to remove equipment from the outside of the building
09-03-18 18:10 Ken back from EY
09-03-18 18:21 Matt to LVEA to look for iLigo TCS lasers
09-03-18 18:22 Travis and Betsy to EY for first contact
09-03-18 18:26 Terry to HAM6 SQZ table
09-03-18 18:29 Peter to TCS chillers to check hi and low setpoints
09-03-18 18:32 Fil is done ay EY and is now at MX
09-03-18 18:43 Chandra to MY
09-03-18 18:44 Karen to MY
09-03-18 18:44 Matt is back from the LVEA
09-03-18 18:50 Karen leaving MY
09-03-18 19:14 Fil done at MX now at MY
09-03-18 19:32 Mark done installing table over HEPI peer on North side of HAM6
09-03-18 19:32 Chandra to LVEA to spin up the Y beam manifold pump
09-03-18 19:46 Richard back from outbuildings
09-03-18 20:04 Ed and Jason out of PSL for lunch
09-03-18 20:16 Liz going to outbuildings for access control work
09-03-18 20:25 Pcal crew back from EX
09-03-18 20:37 Betsy and Travis to EY
09-03-18 20:38 Nutsinee to HAM6
09-03-18 20:48 Fil and Liz to MY
09-03-18 20:58 TVo and Olivia to LVEA to turn on a CO2 laser
09-03-18 21:14 TVo and Olivia back from LVEA, TCSY laser was turned on
09-03-18 21:18 JeffB to LVEA to reset Dust5
09-03-18 22:10 JeffB to EX to reset dust monitor
09-03-18 22:19 Nutsinee to HAM6
09-03-18 22:26 EY temperature has been giving alarms since 22:00 for high temperature
09-03-18 22:27 Bubba took a look and the temperature has leveled out at about 66F
09-03-18 22:27 EY setpoint is 65F so temperatures there should be coming down
09-03-18 22:56 Travis and Betsy back from EY
09-03-18 22:56 Fil and Liz at EY
09-03-18 23:03 Ed and Jason to PSL enclosure
09-03-18 23:07 Mark to Cosmic Ray detector in LVEA and CER
09-03-18 23:22 Mark done in LVEA
09-03-18 23:35 FIl and Liz back from EY and all other outbuildings
Images attached to this report
Comments related to this report
cheryl.vorvick@LIGO.ORG
- 16:19, Friday 09 March 2018 (40938)
Link
00:18 Janson and Ed out of the PSL
cheryl.vorvick@LIGO.ORG
- 16:51, Friday 09 March 2018 (40939)
Link
00:51 Chandra heading to MY