Reports until 09:35, Monday 12 March 2018
H1 General
edmond.merilh@LIGO.ORG - posted 09:35, Monday 12 March 2018 (40958)
Morning Meeting Minutes

VAC - pumping down in the corner station. Bake is going slow at MY

PSL - ongoing 70W installation work. Mode matching into the new amplifier is the plan for today.  Camera work in PSL; moving GigE cameras to new locations

SQZ - squeezer work will continue. If there's a break in it SEI will take the advantage to do balancing

SUS - OPO Model work (Tues)

SEI - Target of opportunity work contingent on squeezer work. ISI model changes contingent on ECR

CDS Ele - Access control work will be going on at MY

EX - Extraction of the Quad

EY - Pcal maintenance work this week. Vac work this week.  SUS closeout w/doors today.

HVAC- work ongoing in optics lab

HAM6 - Target of opportunity work: