kyle.ryan@LIGO.ORG - posted 14:45, Friday 16 March 2018 (41042)
Shut down Y-end purge-air
Purge-air flow was brought to a halt once the BSC door was installed earlier this week -> Isolated purge-air from VE via closing vent/purge isolation valve.  Shut down purge-air supply.  We will restart as required to install the refurbished 2500 l/s ion pump, new gate valve, nipple and chevron baffle as soon as all items have arrived at LHO.