H1 SYS (SYS)
slawomir.gras@LIGO.ORG - posted 16:48, Tuesday 27 March 2018 - last comment - 21:23, Tuesday 27 March 2018(41168)
AMD installation in progress
Sebastien, Betsy, and Slawek


We installed AMD 1 and 2 on ETMy today. It went very well, no issue to report.  We applied the required force on each AMD (~250 g). The bond looks homogeneous with tiny excess epoxy ring around the AMD base, as expected. Curing will take 24 hours. We did the dynamic test of the epoxy before installation and it was successful. Installation of AMD 3 and 4 is scheduled for Thursday morning (3/29).
Comments related to this report
betsy.weaver@LIGO.ORG - 21:19, Tuesday 27 March 2018 (41175)

Below are pictures of the first AMD and it's tooling installed on the left flat of ETMY (Left as viewed from the standard sus back).

Images attached to this comment
betsy.weaver@LIGO.ORG - 21:23, Tuesday 27 March 2018 (41176)

And below are the first AMD and tooling installed on the Right flat of the ETMY also installed today.

Each flat gets one more, scheduled for a Thur install with Slawek and Seb.

Images attached to this comment