kyle.ryan@LIGO.ORG - posted 18:06, Monday 02 April 2018 (41258)
3 of 3 OMC NEG pump particulate mitigation exercise completed
Longer "blow out" durations following activations further reduced counts.
Pumps will need to be activated just prior to exposure to VE if/when entering service.