Reports until 16:03, Thursday 05 April 2018
H1 General
yannick.lecoeuche@LIGO.ORG - posted 16:03, Thursday 05 April 2018 (41310)
Shift Summary - Day

TITLE: 04/05 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC

STATE of H1: Planned Engineering

INCOMING OPERATOR: None

 

LOG:

13:20 (6:20) Peter to PSL

14:07 (7:07) Chris, Mark, Tyler to LVEA -- HAM5 door removal

14:12 (7:12) Kissel, Warner to HAM5 -- locking HEPI

14:30 (7:30) Jeff to HAM5 -- check CC kit

14:35 (7:35) Peter out of PSL

14:45 (7:45) Jeff out of LVEA

14:45 (7:45) Jeff to EY -- reset dust monitor

15:00 (8:00) Kissel, Warner back from HAM5

15:00 (8:00) Start of shift

15:29 (8:29) Chandra to EY -- start pumpdown

15:42 (8:42) Fil to EY -- assist with dust monitor reset

15:43 (8:43) Sheila to LVEA -- ask about cable

15:49 (8:49) Karen to EY, MY

15:52 (8:52) Kissel to LVEA -- make sure there’s a phone in the LVEA

15:59 (8:59) Kissel and Peter to PSL -- lock out rotation stage

16:07 (9:07) Kissel and Peter out of PSL -- shutter is closed

16:11 (9:11) Jeff back from EY

16:33 (9:33) Bubba to HAM5

16:37 (9:37) Kissel, Warner to LVEA -- contamination control/lock HAM5 ISI

16:42 (9:42) Bubba back from LVEA

16:55 (9:55) Sheila transitioning LVEA to Laser Hazard, starting HAM6 alignment

17:15 (10:15) Keita to HAM6 -- assist with alignment

17:26 (10:26) Mark, Tyler out of LVEA -- doors off

17:43 (10:43)  Mark, Tyler to LVEA -- moving IP3

17:56 (10:56) Sebastien, Dan to LVEA

17:58 (10:58) Richard to MY

18:00 (11:00) Tyler out of LVEA

18:03 (11:03) Tyler to LVEA --continue IP3 work

18:08 (11:08) TJ to HAM6

18:16 (11:16) TJ out from HAM6

18:22 (11:22) Terra, Evan, Miriam, Jenne to HAM6

18:27 (11:27) Karen to H2 Electronics Room

18:31 (11:31) TJ to HAM6 -- finding wrench

18:51 (11:51) Evan, Miriam, Jenne out of HAM6

18:55 (11:55) Terra out of HAM6

19:33 (12:33) Mark, Tyler out of HAM6 -- lunch break

19:45 (12:45) Sebastien, Dan out of LVEA

20:03 (13:03) Jim to EX -- replace BHCS on PCal periscope

20:38 (13:38) Mark, Tyler into LVEA -- attach valve

20:42 (13:42) Kissel, Keita, Sheila, TJ, Nutsinee, Terry, Daniel out of LVEA -- lunch break

20:49 (13:49) Sebastien, Dan into LVEA

21:06 (14:06) Kissel, TJ, Sheila, Keita to LVEA

21:07 (14:07) Peter to PSL enclosure

21:11 (14:11) Georgia to HAM5

21:15 (14:15) Jason to PSL enclosure

21:17 (14:17) Chandra to MY, EY

21:29 (14:29) Jim back from EX

21:42 (14:42) Georgia out of HAM5

21:58 (14:58) Terra to LVEA

22:05 (15:05) Tyler, Mark out of LVEA

22:05 (15:05) Tyler, Mark to MY, EY

22:32 (15:32) TJ out from HAM5

22:34 (15:34) Dan, Terra, Sebastien out of LVEA

22:41 (15:41) Jeff and Chris to HAM6 -- contamination control

22:47 (15:47) Sheila transitioning LVEA to Laser Safe

22:49 (15:49) Jeff back from HAM6

22:51 (15:51) Terry, Nutsinee back from HAM6

22:55 (15:55) Chris to LVEA -- put HAM5 doors on

22:58 (15:59) Tyler, Mark to LVEA -- put HAM5 doors on

23:00 (16:00) End of shift