keita.kawabe@LIGO.ORG - posted 17:53, Friday 07 September 2012 (4133)
fiber swapped but no PLL today.

Fiber was swapped from optics lab refcav to the PSL.

At the fiber patch panel in the MSR, the power we're getting from the optics lab refcav was about 3.3mW while our new PSL fiber provides 1.1mW or so.

Everybody had something else to do, so nobody was able to take care of the PLL. We'll continue working on it on Monday.