Ops Shift Log: 04/13/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for vent, upgrades, and changes
Intent Bit: Engineering
Support: X
Incoming Operator: N/A
Shift Summary: Re-welding fibers and installation work at End-X, Squeezer work at HAM5/6, and vacuum upgrades across site.
Activity Log: Time - UTC (PT)
15:00 (08:00) Start of Shift
15:24 (08:24) Add 150ml cooling water to Crystal Chiller
16:01 (09:01) Karen – Finished at End-Y
16:17 (09:17) Karen – Finished at Mid-Y – Going to VPW
16:21 (09:21) Chandra – Going to Mid-Y
16:26 (09:26) Peter – IN PSL enclosure
16:31 (09:31) Georgia & Sebastian – Going into the Squeezer Bay – Will be using the CO2 Laser
16:49 (09:49) Koji – Going to PSL enclosure
16:52 (09:52) Georgia and Sebastian – Out of the LVEA
16:58 (09:58) TVo & Daniel – Going to the Squeezer Bay
17:01 (10:01) Marc – Going to the vault to take some measurements
17:12 (10:12) Rich A., Luis, Niko, Georgia – Going to End-X
17:13 (10:13) Sabastian – Going to Squeezer Bay
17:33 (10:33) Sheila – Going to HAM6
17:42 (10:42) Jason – Out of the LVEA
17:54 (10:54) Marc – Back from the vault
18:13 (11:13) Mark & Tyler – Going to End-X to investigate a water leak
18:17 (11:17) Sheila – Out of the LVEA
18:25 (11:25) Sheila & Craig – Going into the LVEA
18:30 (11:30) Rich, Luis, Niko, Georgia – Back from End-X
18:52 (11:52) Daniel, Sabastian, & TVo – Out of LVEA – CO2 laser is off
19:00 (12:00) Dave – Going to End-X to look at computer racks
19:10 (12:10) Peter & Koji – Out of the PSL enclosure
19:23 (12:23) Dave – Back from End-X
19:45 (12:45) Georgia & Sabastian – Going to Squeezer – will be operating CO2 laser
20:27 (13:27) Chandra – Going into the HAM4 and HAM5 area for leak checking
20:31 (13:31) Daniel – Going to Squeezer Bay
20:56 (13:56) Peter – Going into the PSL enclosure
21:00 (14:00) Turn over to Patrick