(Gray, Radkins)
In preparation for sealing up HAM6, SQZT6 Table location marked (hung plumb bob off 3 corners and marked on floor. The table is currently on its wheels (vs on the fixed feet which are landed on the silver feet bases when tables are finally located.). Marks made today are for the X-location of the table. When table can be moved into its final location, we'll use the marks and roll the table in the +Y direction closer to HAM6.
Next Items for this table (& ISCT6...which already had it's location marked):
Secure all optical / electrical components
Disconnect electronics cable connections, stow cables safely
(Carefully) Disconnect optical fiber connections, stow fibers safely
Then we'll move both tables out of the way for HAM6 door installation.