H1 General
cheryl.vorvick@LIGO.ORG - posted 13:43, Monday 30 April 2018 (41746)
Morning Meeting:

Summary:  We are venting the Vertex to enter HAM5 and access both ITMs, hardware install in all three chambers.  Parasitic vacuum work on the Input Mode Cleaner beam tube to replace IP gate valves, work on the PSL continue with mode matching into the PMC, fiber pulling at EX, contractors on site for Richard and Bubba, and APS continues their work (contractor, access control).

Access to MY: Chandra requests that any activity at MY be cleared with her, due to the ongoing bakeout.

VAC:

SUS:

PSL:

Other: