Reports until 16:28, Monday 30 April 2018
LHO VE (CDS, VE)
patrick.thomas@LIGO.ORG - posted 16:28, Monday 30 April 2018 - last comment - 17:25, Monday 30 April 2018(41751)
Replacing PT170 gauge
Part of WP 7519.

Gerardo has gone out to the LVEA to replace PT170 with a BCG450 Inficon gauge (It is currently a BPG402 Inficon gauge). When he is done I will update and restart the software on h0vaclx to match the change.
Comments related to this report
patrick.thomas@LIGO.ORG - 17:25, Monday 30 April 2018 (41754)
Work complete. No issues seen. DAQ restart needed at some point.