Current Issues: - FMCS was down when I came in today - it's still down... - instrument air at Mid-X had a real failure that Kyle is working on Morning meeting notes: OAT: noise until 1PM is OK, then Keita needs quiet time HAM3: MC2 - will be fixed as directed after transfer functions HAM1: passive stack install is ongoing Cabling: ISC rack install ongoing IO: Faraday work continues Viewports: Test cap used to test inside glass of PSL input viewport. Outside - glass mount modified to connect inside volume to vacuum. Light pipe left off until light needed in chamber. EX: prep for cleaning and measurements cleaning may start tomorrow ISC SLED: assembly is ongoing General: ISC table is still open in LVEA, with optics exposed Shipping for Squeezer is planned Controls Solutions - here to muck with HVAC to check sensors for flow Electric - FM200 system check tomorrow Ray Pollen Construction here to fill water tanks in outbuildings tomorrow Issue from yesterday: PSL AC off, causing temperture increase in PSL laser room by 8 degC. Why did AC issue with PSL happen? We don't fully understand the systems. HVAC system was in alarm. Readings for temperatures comes through BECKOFF, which was powered off last Friday, and when powered up again, didn't read new temperatures, but just braodcast the last known state, so was giving bogus data, so we didn't get an alarm, and didn't know the AC wasn't working.