Reports until 16:28, Wednesday 02 May 2018
LHO General
patrick.thomas@LIGO.ORG - posted 16:28, Wednesday 02 May 2018 (41810)
Ops Shift Summary
14:52 UTC Mark into LVEA
14:52 UTC Peter to PSL enclosure
Hugh running transfer functions on HAM4 ISI
15:39 UTC APS through gate
15:39 UTC Chris opening inner rollup door to LVEA
15:45 UTC Chris done
15:58 UTC Stephen, Angus, Jason, Travis (weld crew) to end X
16:51 UTC Karen to mid Y, cleaning outside of VEA
16:55 UTC Hugh to HAM5
17:06 UTC Ken and Chandra to mid Y
17:25 UTC Visitor from Mid Columbia Engineering through gate
17:35 UTC Chris to LVEA to help Tyler with ion pump removal
18:01 UTC Kyle to end X to measure purge air humidity
18:02 UTC Bubba WP 7529
18:07 UTC Tour in CR
18:20 UTC Tour leaving CR
18:52 UTC Hugh out of HAM5
19:03 UTC Mark and Tyler out for lunch
19:17 UTC Travis and Angus back from end X
19:22 UTC Kyle back
Peter out of PSL enclosure
19:29 UTC Daniel to IO racks to take cable length measurements
19:39 UTC Daniel done
20:08 UTC Mark to LVEA to work on IP1
20:08 UTC Visitor through gate to see Filiberto
20:11 UTC Peter to optics lab and then PSL enclosure
20:21 UTC Chris to LVEA to help Mark with IP1
20:37 UTC Jason to end X for fiber welding
20:49 UTC Hugh to end X mechanical room
21:10 UTC Sebastien, Slawek, Betsy to LVEA
21:12 UTC Hugh to end Y
21:16 UTC Visitor from University of Washington through gate
21:22 UTC Filiberto to vault and mid X
21:41 UTC Mark and Chris done. IP1 is done. IP2 is on floor. South bay crane locked out.
Hugh back
22:00 UTC Site weekly meeting
22:05 UTC Filiberto back
Slawek, Sebastien, Betsy back
23:18 UTC Sheila transitioning LVEA to laser hazard