Reports until 09:55, Monday 07 May 2018
H1 AOS
jeffrey.bartlett@LIGO.ORG - posted 09:55, Monday 07 May 2018 (41857)
09:00 Meeting Minutes
UNTIL FURTHER NOTICE, DO NOT DRINK TAP WATER.
There are some elevated contaminate levels in the water, which are being addressed.
 
Please remember to close your completed work permits.
 
 
VAC:
Torqueing bolts on BSC 1 & BSC3
Starting the CS pump down
 
PSL:
Cheryl will be working on IO alignment and PD installation in the PSL enclosure

 

CDS:

Work on access control system continues. These is cabling pulling in the LVEA and installation work in the staging building.
 
SUS:
ETM-X installation and alignment work
 
SEI:
Hugh is swapping the CPS rack for ITM-X
 
MISC:
Dick G. continuing work on RF measurements
 
Tuesday Maintenance:
Several model restarts
Guardian updates
PSL ISS model work