Reports until 09:34, Thursday 17 May 2018
H1 General
Link
cheryl.vorvick@LIGO.ORG -
posted 09:34, Thursday 17 May 2018
(42037)
Morning Meeting:
Planned Activities:
LVEA: going back to Laser Hazard
DRMI: needs PSL beam, plan is to work on this today, tomorrow, and possibly Monday
HAM6:
all extra hardware is out
Jimm wants to float the ISI and take transfer functions
when laser hazard again, crew will take beam profiles
North dorr likely to be put on tomorrow
PSL: no work in the enclosure today, DRMI is priority, multiple days set aside next week
LSB: Suresh is planning to work in the lab this weekend
GC: Ryan is addressing network issues, and may change/add some hardware