This morning, Travis and Gabriele finished taking the in-air suspended violin mode measurements on ETMX.
This allowed us to continue rebuilding the QUAD structure, adding the sleeve stiffener, cross braces, wedges, and vibration absorbers. Thanks to Chris who took my place during the awkward sleeve maneuver - he and Travis did the usual: remove 2 of the heavy chamber floor panels, stand straddling the gap to dead lift the sleeve using one hand each, securing with screws by the other hand. Thanks Chris!
Next up EFM install (TUE), BRD tuning and install (TUE/WED), B&K stuff (WED), ISI rebalance (WED/THUR), FirstContact (THUR/FRI), closeout stuff and door on (FRI).