patrick.thomas@LIGO.ORG - posted 09:31, Monday 04 June 2018 (42304)
9 AM meeting notes
Preparing to pump end X
In process of opening GV12
Pumping end Y

DRMI/EY commissioning
DRMI locking, ASC WFS not converging
EOM swap -> possible phase difference

PSL ISS commissioning

CP ion pumps installed and pumping

ISCT1 table alignment ongoing

mid Y CP4 oven work is done

Chiller in fiber welding lab died, moving one from end X

Tuesday: LASER SAFE
Unlock HAM 5/6 HEPI, check range of motion
Pulling fibers in MSR (WP 7617)
Swapping controllers for illuminators
OMC/AS-C whitening chassis swap
Resume filter swapping of end X HEPI