Reports until 09:50, Friday 21 September 2012
H1 AOS
betsy.weaver@LIGO.ORG - posted 09:50, Friday 21 September 2012 (4264)
BSFM02 (I1 BS)

Travis, Betsy

The BS which had been built for H1 on the solid stack/test stand in the LVEA is now destined for India.  (The FMy from BSC8 is due to become the new H1 BS.)  Travis has resumed work on the BS in order to finish it and stow it for India, thus making space for the BSC8 rework for H1.  In line with the standard way we had been naming suspensions, this BS is now being dubbed "BSFM02" as it will be built and tested only to Phase 1 prior to storage.  BSFM02 has been coarsely aligned.