Displaying report 1-1 of 1.
Reports until 09:54, Monday 16 July 2018
LHO General
corey.gray@LIGO.ORG - posted 09:54, Monday 16 July 2018 (42913)
Monday 9am Meeting

(Jeff K running meeting.)

Critical Work:  PSL & Opening Arms

Safety/Site Note:  Unescorted person walked around site & in OSB last week.  Jeff 

PSL Power Stabilization: Peter

Opening Arms:  (Kyle)

TCS: (Thomas)

OPERATORSBack to COMMISSIONING!!  (This was also reiterated in the Ops Meeting last week.)   

Other:  

SEI:

MAINT:  4hrs only!  (depending on PSL work though)

Displaying report 1-1 of 1.