(Jeff K running meeting.)
Critical Work: PSL & Opening Arms
Safety/Site Note: Unescorted person walked around site & in OSB last week. Jeff
PSL Power Stabilization: Peter
- AOM driver install & align (wait until Tues Morn)
- Jeff B
Opening Arms: (Kyle)
- Can open y-arm. (TCSy/ITMy viewport is complete) Possibly open this morning.
- Prob open x-arm (EX), after some investigation.
TCS: (Thomas)
- Want to check beam qual on TCS (since tcsy wasn't great); CO2X work permit coming.
- Hartman alignment after arms open
OPERATORS: Back to COMMISSIONING!! (This was also reiterated in the Ops Meeting last week.)
- Keep ALL SUS/SEI DAMPED!
- Use Reservation System!
- For Everyone: No disruptive work!
- Aim for Maintenance to be completed by noon.
Other:
- ITMx oplev needs realignment after x-arm opened (tomorrow?)
- Outreach International Teacher Program starts this week. Tour today 11-1pm in LVEA & end station.
SEI:
- HEPI trips: EX fixed & EY next. Call Hugh next time!
- HEPI is related to low voltage glitch in hot weather
MAINT: 4hrs only! (depending on PSL work though)
- PSL ISS work (Peter, jason, 3hrs)
- Inventory work HEPI...should be quiet (hugh, 3hrs, B1B3H6)
- Quad model (JK, 10min)
- Charge ETMs (Georgia or operators, 2hrs)
- PSL cabling with peter (Richard)
- PEM cables runs (2hrs)
- Moving TMDS tables, marking location (Kyle,M&M, 1hr)
- replacing HVAC in machine shop at staging (Bubba)
- Should stay Laser HAZARD.