TITLE: 07/25 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
15:30 Vanessa out to EX - cleaning
16:00 BRS sensor correction turned off - suspect cleaning activities caused some perturbance at EX. Perhaps some seismic concessions to be made for these morning activities.
16:32 pursuant to the last entry: ISI and TMS at EX tripped. Jim reset ISI wd, straight away. TMSX wd was reset 27 minutes later - verbal alarms volume was turned down.
16:54 Richard out to EX to talk to the wind-fence crew - Mark, Tyler, and Chris.
17:07 Dave B restarting digital video camera server
17:16 Haocun out to HAM6 area
17:17 Fil out to CER to power cycle illuminator ckt for BSC2
17:20 Fil back
18:45 Jeff B out to clean area
18:50 Jeff back
19:15 Georgia and Dave out to ISCT1
19:52 Georgia back
19:55 Carlos out to LVEA ISCT1 to verify operation.
20:01 Kyle out to EX vea
20:06 NDS server restart
20:15 Haocun back
20:24 Carlos back
20:36 Kyle back from EX
20:55 HWS team out to LVEA - TJ, Georgia, and Daniel
21:13 Gerardo out to both arms xx-8(where solar panels are) to visit ion pumps
21:59 HWS team out
22:00 Weekly Site Meeting