Displaying report 1-1 of 1.
Reports until 10:35, Friday 03 August 2018
H1 TCS (AWC, TCS)
thomas.vo@LIGO.ORG - posted 10:35, Friday 03 August 2018 (43223)
ITMX CO2X First Look

[TCS Team]

The CO2X laser tripped last night before we could not inject some heating for a couple minutes.  However, the pre-heating guardian for CO2X was turned on for about 3 hours at 500 milliwatts with central heating so we can get some preliminary information about the centering.

This is the heating up:

This is the cool down:

There doesn't seem to be any apparent clipping/fringing of the CO2 beam, and centering isn't terrible.  The edge on the upper right side is due to clipping of the HWS beam.

Images attached to this report