Removed IP11 old controller, DualVac type, and replaced it with a new Gamma controller. Reconfigured wiring at the breakout box, and landed the wires for the new controller. All that freed up multiple wires at the breakout box, which are going to be used to take other signals to the vacuum rack, for example readback signals from the controller for IP15 (Ion pump at Y2-8).
While replacing this controller, the controller for one of the NEGs at Y-End (NEXTorr neg) was moved from its temporary location to its permanent location, a rack that will house all controllers for this station, see photo.
Beckhoff system at the vacuum rack will need to be reconfigured for the new controller readback signals to make sense, the controller is ON and IP11 is pumping on a very small volume, since it is isolated from the main volume via its gate valve.
This closes WP#7755.