jeffrey.bartlett@LIGO.ORG - posted 08:03, Friday 17 August 2018 (43483)
Ops Day Shift Transition
Ops Shift Transition: 08/17/2018, Day Shift 15:00 – 23:00 (08:00 -16:00) - UTC (PT)
State of H1: Unlocked for post vent commissioning  
Intent Bit: Commissioning
Weather: There has been a break in the poor air quality due to a low pressure system that moved into the area last night. Bring winds and some rain it has helped to clear the air, at least for a couple of days. There is a slight change of thunderstorms or localized rain before noon. Temperatures are forecast to be in the mid-90s under clear skies, provided the smoke and haze do not move back in. Winds are ranging up to a Moderate breeze, with higher gusty conditions expected.        
Primary 0.03 – 0.1Hz: X
Secondary 0.1 – 0.3Hz: X
Outgoing Operator: N/A
Quick Summary: Peter has been in and out of the PSL taking measurements and commissioning work has started.