Displaying report 1-1 of 1.
Reports until 16:07, Friday 17 August 2018
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:07, Friday 17 August 2018 (43498)
Ops Day Shift Summary
Ops Shift Log: 08/17/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for post vent commissioning
Intent Bit: Commissioning
Support: N/A
Incoming Operator: N/A
Shift Summary: Commissioning work on locking for most of the day. Work on HWS and Squeezer. PSL was tripped off by the ACS installation work in the Diode room. Wiring was repaired and laser is back up. Further installation work in the diode room has been postponed until late next week.
 
Activity Log: Time - UTC (PT)
11:50 (04:50) Peter – Into the PSL to take measurements
13:50 (06:50) Peter – Out of the PSL enclosure
14:00 (07:00) Karen – Cleaning at End and Mid-Y
14:30 (07:30) Karen – Finished cleaning on Y arm – back to CS
14:58 (07:58) Vanessa – Going into the LVEA for cleaning
15:00 (08:00) Start of shift
15:12 (08:12) Nutsinee – Going to Squeezer table
15:45 (08:45) TVo – Turning on CO2-X laser
16:00 (09:00) TVo – Out of the LVEA
16:00 (09:00) Karen – Cleaning in the H2 and “lightbulb” buildings
16:22 (09:22) Karen – Back from the H2 building
17:02 (10:02) Dan – In LVEA at HWS table
17:09 (10:09) Dan – Out of the LVEA
17:40 (10:49) Filiberto – Going into the LVEA to recover equipment
18:00 (11:00) PSL down – Peter trying to restart
19:30 (12:30) PSL back up – Access control system install in diode room tripped off the laser
20:06 (13:06) Haocun, Nutsinee, & Terry – Going to the Squeezer table
22:03 (15:03) Kyle – Going to all buildings to pick up N2 delivery paperwork
22:18 (15:18) Dick – Going to PSL racks for RF hunting
22:39 (15:39) Marc – Going to PSL racks to work with Dick
22:52 (15:52) Kyle – Back from paperwork mission
23:00 (16:00) End of shift
Displaying report 1-1 of 1.