Reports until 15:14, Tuesday 02 October 2012
LHO General
jodi.fauver@LIGO.ORG - posted 15:14, Tuesday 02 October 2012 (4356)
Packing optics from OSB Optics Lab
Cheryl and I spent some time working on the iLIGO Core Optics today. This morning, we verified the identity and location of the optics going to KAGRA. After lunch and re-reading the packing procedure, I verified that two of the KAGRA optics are ready for shipment. I also removed all old labels from the cake tins to avoid confusion on the part of those receiving optics from us. In addition, the Apollo crew wiped down the grey optics shipping cases and moved them into the LVEA. I moved the cases around to the cleaning space just outside the H1 electronics room. We will inspect, document and attempt to pack two KAGRA optics tomorrow morning.