Announcement: Fire late Fri night w/ water pump alarms following.
- If any one sees a fire, let Jeff Jones know, so they can address regarding operations. One can call 911, or non-emergency number, which is listed in our phone roster.
Commissioning:
- Sat: investigate ITM/ETM alignments, then PSL issues.
- Check White Board for this week's activities
Tues Maint
- Time: Not clear....4hrs or more?
- Transition to Laser SAFE first thing in morning (get work permit filed early)
- Gate Valves Closed
- Charge (normal one)
- SEI CPS (power cycling chassis, re-seating board in chasis, etc.)
- BSC T240's recentering
- PEM accel ham6 cable run out
- EY ESD power supply cable pulling
- Kepco power supplies (time permitting)
- VAC: LVEA leak check which requires gate valve closing, need spinning corner turbos on Mon afternoon (commissioning says should be OK),
- regenerate neg#1 & heat up for an hour
- Guardian reboots (TJ)
Other Items:
- Safety Review occurring later this week on site.
- All Hands Meeting on Friday in MPR.
- Safety: Be safe outside even when not at work (be careful with household machines/tooling, as a pedestrian, etc.)