Displaying report 1-1 of 1.
Reports until 22:27, Tuesday 18 September 2018
H1 CDS (DAQ)
david.barker@LIGO.ORG - posted 22:27, Tuesday 18 September 2018 - last comment - 22:37, Tuesday 18 September 2018(44048)
CDS upgrade summary

WP7815

Rolf, Keith, Dave, Jonathan, Jamie, Richard, Fil, Ed 

Today we did a major upgrade to the CDS system:

After the IFO was placed in a safe state, we stopped all models and powered down all computers with Dolphin cards. We stopped DHCP running on the old boot server (h1boot) and started it on the new boot server (h1boot1). We rebooted all the non-Dolphin systems (SUS-AUX) to gt3.0.8/rcg3.4.2 and restarted the DAQ.

Rolf, Jonathan, Fil and Ed upgraded the MSR, Keith upgraded the software systems, Dave and Jamie upgraded the end stations. At each location:

The long-range Dolphin server (h1cdsrfm) had been installed on Monday, today its Dolphin cards (both local and at the end stations) were connected to their respective Dolphin switches.

The h1ioplsc0 model was modified to run as a timing server for h1oaf1.

We discovered timing issues with the mid station PEM systems. The remoteGPS function was not obtaining the correct time from h1dc0 via EPICS channel access. When this was turned off, the GPS time was one second too slow. A modified RCG-3.4.3 was installed to advance the GPS time by one second and h1ioppem[mx,my] were built against this. The Mid Station PEM systems are now running correctly.

*V4 computer upgrade:

Initially we were to upgrade 10 front end computers to V4. However we found that the V4 computers could not detect the cards in the IO Chassis if the OneStop fiber transceivers were from 2011 or earlier. Testing on h1iscex and h1susex showed that 2012 and 2015 fibers worked. Because running new OneStop fiber at the end stations is relatively easy (adjacent rooms, open access cable trays) , Fil and Ed ran two 2012 fibers at each end station for the SUS and ISC computer upgrade. Running new fibers between the MSR and CER in the corner station is more problematical, so the two computers which had been upgraded to V4 at that point were returned to their original hardware for now.

The upgrade was completed and the system handed over to the control room at 16:59 PDT.

Fixed:

Still To Do:

Install new h1oaf1 front end computer, this is a Dolphin only machine (no IRIG-B timing or IO Chassis) which will get its timing from h1ioplsc0.

Comments related to this report
david.barker@LIGO.ORG - 22:30, Tuesday 18 September 2018 (44049)

Add to To Do List:

IPMI cables for h1sus[ex,ey] and h1isc[ex,ey] (new V4 computers)

david.barker@LIGO.ORG - 22:32, Tuesday 18 September 2018 (44050)

At the end stations, the installed V4 machines only have USB ports, therefore the PS2-type KVM cables were replaced with USB-type cables at these locations.

david.barker@LIGO.ORG - 22:37, Tuesday 18 September 2018 (44051)

Three modified models were restarted today:

h1isc[ex,ey] with Sheila's modifications (circulating power calculation)

h1pemcs, Dave added new Accelerometer channels

Displaying report 1-1 of 1.