Chamber Cleaning starting before 8 (Christina, Vanessa, Karen.) VE venting volume around 8am (Chandra.) Venting completed and East Door removed ~9:30, Kyle Gerardo, Bubba.) Dust Monitor counts 30 & 30 in clean room just before door removal. After removal, Dust counts in chamber 10 & 10.
Fiber change out from ~10am to 12:40: Old fiber & Feed Thru removed, Test fiber/FT installed/removed, Real deal fiber/FT installed. Feed Thru bolts remains just snug (Sheila, Fabrice, Haocun, Nutsinee.)
SQZ has gone hazard and work continues.
There was no dust witness wafer to be seen from the east door. We'll put one in at close out for the future.