Reports until 16:09, Monday 12 November 2018
H1 AOS (ISC, SEI, SQZ, SUS, VE)
hugh.radkins@LIGO.ORG - posted 16:09, Monday 12 November 2018 - last comment - 08:39, Tuesday 13 November 2018(45235)
WHAM6 Vent Activities

Chamber Cleaning starting before 8 (Christina, Vanessa, Karen.)  VE venting volume around 8am (Chandra.)  Venting completed and East Door removed ~9:30, Kyle Gerardo, Bubba.) Dust Monitor counts 30 & 30 in clean room just before door removal.  After removal, Dust counts in chamber 10 & 10.

Fiber change out from ~10am to 12:40: Old fiber & Feed Thru removed, Test fiber/FT installed/removed, Real deal fiber/FT installed.  Feed Thru bolts remains just snug (Sheila, Fabrice, Haocun, Nutsinee.)

SQZ has gone hazard and work continues.

Comments related to this report
hugh.radkins@LIGO.ORG - 08:39, Tuesday 13 November 2018 (45249)

There was no dust witness wafer to be seen from the east door.  We'll put one in at close out for the future.