Reports until 08:12, Tuesday 13 November 2018
H1 General
edmond.merilh@LIGO.ORG - posted 08:12, Tuesday 13 November 2018 (45247)
Shift Transition - Day

TITLE: 11/13 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 6mph Gusts, 4mph 5min avg
    Primary useism: 0.03 μm/s
    Secondary useism: 0.25 μm/s
QUICK SUMMARY:

14:15 Peter out to PSL - remounting 70W amp

14:30 Chris S out to LVEA - HAM6 scaffold

15:07 Chris back

15:30 Bubba and Chris out to LVEA- set HAM6 end cap door down on pallets'

16:00 Jeff B out to LVEA