Reports until 16:00, Wednesday 14 November 2018
H1 AOS (ISC)
georgia.mansell@LIGO.ORG - posted 16:00, Wednesday 14 November 2018 - last comment - 08:21, Thursday 15 November 2018(45279)
ISC HAM1 work today - POP beam diverter replaced, inital tests of LSC-REFL_B completed

Keita, Richard, Corey, Craig, Georgia

Images attached to this report
Comments related to this report
keita.kawabe@LIGO.ORG - 16:06, Wednesday 14 November 2018 (45281)

For now,

  • REFL B is only held at an approximate place using just one screw.
  • 50:50 BS for REFL_A REFL_B splitting is yet to be installed.
  • Black glass beam dump for REFL_B is yet to be installed.
  • 5-way coax continuity check was done for the feedthrough but we don't know if the RF connection at the diode is good.

These are finalized/installed/checked on Saturday after the PSL beam becomes available and IMC locked in vacuum.

 

alena.ananyeva@LIGO.ORG - 08:21, Thursday 15 November 2018 (45298)
Here is some experience on cleaning the foggy patterns on black glass:
https://nodus.ligo.caltech.edu:8081/OMC_Lab/283
https://nodus.ligo.caltech.edu:8081/OMC_Lab/283