Ops Shift Log: 11/14/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for vent
Intent Bit: Maintenance
Support: N/A
Incoming Operator: N/A
Shift Summary: Vent and vent close out activities dominated the day’s work efforts.
Activity Log: Time - UTC (PT)
14:25 (06:25) Peter – In the PSL enclosure
15:11 (07:11) Vanessa – Into the LVEA
15:13 (07:13) Karen – Into the LVEA
15:18 (07:18) Chris – Tumbleweed bailing on X-Arm
16:00 (08:00) Start of Shift
16:12 (08:12) Karen & Vanessa– Finished in LVEA
16:20 (08:20) Gerardo – Going to HAM1 to work on doors
16:22 (08:22) Karen – Going to End-Y
16:31 (08:31) Sheila – Transition LVEA to Laser Safe (WP #7943)
16:35 (08:35) Chris – Finished with tumbleweed bailing
16:48 (08:48) Ed – Going to Squeezer Bay to look for cables
16:50 (08:50) Hugh & Corey – Going to HAM1
16:54 (08:54) Charles – Going to HAM1 to observe door removal
17:00 (09:00) Jeff J. – Going to HAM1 to observe door removal
17:03 (09:03) Richard & Ed – Going to LVEA to PSL racks
17:12 (09:12) Niko – Going to HAM1 for cabling & L4C work
17:15 (09:15) Richard & Ed – Out of the LVEA
17:18 (09:18) Marc – Going to End-X to pull a couple of chassis for repair
17:19 (09:19) Karen – Finished cleaning at End-Y
17:22 (09:22) Ed – Going to End-X and End-Y to drop off electrical equipment
17:25 (09:25) Jason – Going to PSL enclosure
17:52 (09:52) Hugh & Sheila – Going to HAM1
17:53 (09:53) Charles & Jeff J. – Out of the LVEA
17:59 (09:59) Hugh – Out of the LVEA
18:00 (10:00) Finished pulling HAM1 doors
18:05 (10:05) Filiberto – Pulling cable at PSL racks
18:14 (10:14) Shelia & Hugh – Out of the LVEA
18:19 (10:19) Ed – Transitioned End-X to Laser Hazard because one table door is unlocked.
Could not find Key at End station
18:25 (10:25) TvO and Dan – Going to TCS tables
18:30 (10:30) Sheila – Transitioned LVEA to Laser Hazard (WP #7944)
18:32 (10:32) Terry – Going to HAM6
18:35 (10:35) Sheila – Going to HAM6
18:38 (10:38) Chandra – Going to End-Y to start turbo
18:45 (10:45) Karen – Cleaning in LVEA around HAM1& Optics Lab
19:11 (11:11) Robert – Into the Diode Room and PSL enclosure to look for noise in PSL cooling system
19:40 (11:40) Chandra – Going to End-Y to work on RGA
19:41 (11:41) Cheryl – Going into the PSL enclosure
19:42 (11:42) Betsy – Going out the HMA1
19:43 (11:43) TvO and Niko – Out of the LVEA
19:47 (11:47) Hugh & contractor – Going to End-X to look at wind fence
19:52 (11:52) Karen –Out of LVEA and Optics Lab
20:02 (12:02) Chris – Back
20:05 (12:05) Betsy – Into the LVEA to check on HAM1 progress
20:10 (12:10) Jason – Out of the PSL enclosure
20:20 (12:20) Betsy – Out of the LVEA
20:30 (12:30) Corey & Niko – Out of the LVEA
20:33 (12:33) Robert – Out of the PSL enclosure
20:35 (12:35) Cheryl – Out of the PSL enclosure
20:58 (12:58) Georgia & Keita – Going to HAM1
21:00 (13:00) Ed – Going to HAM1 to pull cable
21:15 (13:15) Richard – Going to HAM1
21:20 (13:20) Peter – In the PSL enclosure
21:30 (13:30) Terry & Sheila – Out of the LVEA
21:36 (13:36) Robert – Out of the PSL enclosure and LVEA
21:48 (13:48) Hugh, Corey, Niko – Going to HAM1
21:54 (13:54) Chris – Going into the LVEA to look for keys
21:59 (13:59) Chris – Out of the LVEA
22:00 (14:00) Jason – Going into the PSL enclosure
22:04 (14:04) Filiberto – Going to HAM1 for cabling work
22:08 (14:08) Marc – Going to End-X to replace chassis removed this morning
22:14 (14:14) Richard – Going to HAM1
22:16 (14:16) Chandra – Going to End-Y to work on NEG pump
22:38 (14:38) Terry & Sheila – Going to Squeezer table
23:01 (15:01) Ed – Delivering cable to Peter in PSL enclosure
23:12 (15:12) Georgia – Out of the LVEA
23:13 (15:13) Ed – Out of the LVEA
23:36 (15:36) Dave – Going to End-X
23:43 (15:43) Rick – Taking lens to PSL enclosure
23:43 (15:43) Ed – Going to End-X to lock table
24:00 (16:00) End of Shift