TITLE: 11/19 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:29 Peter out to the PSL enclosure
16:30 Keita and Georgia back
17:00 Vent meeting
17:44 Chris out to EY - retrieve swivel hook for forklift
18:00 Jason out to PSL
18:05 Hugh out to LVEA - HAM6 plug in ISI and damp
18:07 Chris back - headed out to LVEA
18:35 Richard out to LVEA - check on FIl doing gnd loop checks
18:39 Karen out to EY
18:40 Corey out to LVEA - HAM1 photos and witness wafer
19:01 Hugh has turrned on HAM6 ISI
19:30 Peter back
20:00 Jason Back
20:27 Jim doing measurements on HAM6
20:28 Jeff out to LVEA to get status on gnd loop checking
20:33 Jeff back
20:45 Everything tripped in HAM2 except HEPI and PRM
21:09 Richard out to LVEA - HAM1 area
21:13 Moved HAM2 to ISI_DAMPED_HEPI_OFFLINE
21:50 Corey and Hugh back
21:53 Peter out to the optics lab
22:04 Jason out to PSL
22:09 Terry and Nutsinee out to the PSL - Squeezer table
22:10 Richard out to LVEA
22:32 Fil and Richard out to HAM6
22:34 Cheryl out to the PSL
22:35 Corey out to HAM1
22:36 Corey out to HAM1
23:17 Chandra out to LOVE - valving in RGA on output tube
23:52 Marc, Richard, and Fil out