Ops Shift Log: 11/29/2018, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for post vent commissioning
Intent Bit: Maintenance
Support: N/A
Incoming Operator: N/A
Shift Summary: Making progress towards stable locking of the IFO.
Activity Log: Time - UTC (PT)
16:00 (08:00) Start of Shift
16:00 (08:00) Karen – Going to End-Y to recover equipment
16:00 (08:00) Vanessa – Into the LVEA for cleaning
17:30 (09:30) Vanessa – Finished cleaning in the LVEA
17:51 (09:51) Karen – Finished in the LVEA – Going to Mid-Y
18:23 (10:23) Karen – Back from Mid-Y
18:34 (10:34) Karen – Going to H2 building
18:40 (10:40) Chandra, Kyle, Gerardo – Going to Bier Garten to check gate valves
18:45 (10:45) Richard – Going to CER
18:46 (10:46) Amber – School tour in CR
18:56 (10:56) Chandra, Kyle, Gerardo – Back from LVEA
19:01 (11:01) Amber – Tour out of the CR
19:04 (11:04) Kyle – Going to Mid-Y
19:08 (11:08) Richard – Out of CER
19:21 (11:21) Haocun – Going to HAM6/Squeezer Bay
20:15 (12:15) Kyle- Back from Mid-Y
00:00 (16:00) End of Shift